UE1100-4-2 Assembly Instructions [Un-assembled] .9mm Buffered Fiber Un-assembled Instructions (16 Steps) Specifications: Type: SC, Field Installable, SC Compatible Mode: Multimode Ferrule Material: All Borosilicate glass ferrule Curing Type: Anaerobic, Epoxy, and UV Curable [Click here for Parts List] [Parts Diagram] [Curing Do's and Don'ts Regarding PVP's UV Connectors] To return to instructions after viewing a diagram, click the back button on your web browser.
Step 1 Slide tapered end of .9mm SC boot onto .9mm cable approx. 6".
Step 2 Slide silver locking piece onto buffered fiber and then slide the spring onto buffered fiber.
Step 3 Measure and mark .750" from the end of the .9mm buffered fiber. Next, strip the buffered fiber from the mark with No Nik stripper.
Step 4 This step is very important. Clean stripped fiber with isopropyl alcohol soaked lint free cloth or a dry lint free cloth. To clean fold cloth in half over fiber and gently squeeze on the fiber and pull it through the cloth. This will clean the fiber of debris.
Step 5 - Gluing the Fiber
(Anaerobic, Epoxy, and UV)
Epoxy Instructions
UV Instructions
Step 6 After curing, carefully rotate spring and silver locking piece up the back end of the ferrule holder until spring seats on holder and locking piece is stopped by the spring. Slide .9mm boot up and slide into place to hold pieces together. [Diagram 1] [Diagram 2] [Diagram 3]
Step 7 Using cleaving tool, lightly score fiber at the point where fiber comes out of ferrule tip. Then pull up on the fiber until it separates from the ferrule. (Note: Do not snap off fiber, pull directly off) (Caution: Cleaved glass fibers can be very sharp.)
Step 8 Align large flat on silver locking piece so that it is parallel with beveled top of white inner housing. Insert silver locking piece into white inner housing and rotate so that small flat of silver locking piece can be seen in the white inner housing.
Step 9 Place PVP rubber mat over PVP lapping plate and line with 15, 5, 1, and .3 micron lapping film.
Step 10 Add 3 drops of water to each lapping film. Place connector into polishing puck.
Note for Steps 11 thru 14: Be sure to blow off connector and puck after each lapping sequence to prevent contamination scratching of core.
Step 11 Do 10 figure 8's using light even pressure, with 15 micron lapping film.
Step 12 Do 14 figure 8's using 5 micron lapping film.
Step 13 Do 15 figure 8's using 1 micron lapping film.
Step 14 Do 15 figure 8's using .3 micron lapping film.
Step 15 Then insert ferrule straight up into 100x Inspection Microscope and inspect fiber core. It should appear like the picture.
Step 16 Final assembly: Place SC shroud (cover) with small end over white inner housing as shown in the Diagram. Make sure that the beveled top side of the white inner housing is lined up with the top of the SC shroud (cover). Push in together until pieces lock.
|
|
[Home] [Products] [Connectors] [Assembly Instructions] [ST* Instructions] [1200 Series] [1500 Series] [1700 Series] [SC Instructions] [FC Instructions]